Q9,paper3,D13. Which once of the following is not a software myth ?



(A) Once we write the program and get it to work, our job is done.
(B) Project requirements continually change, but change can be easily accommodated because software is flexible.
(C) If we get behind schedule, we can add more programmers and catch up.
(D) If an organization does not understand how to control 
Answer D.