Q12,Paper 2, J14. Which one of the following is not a risk management technique for managing the risk due to unrealistic schedules and budgets



(A) Detailed multi source cost and schedule estimation.
(B) Design cost
(C) Incremental development
(D) Information hiding
Answer D.